DGMS Proposed Timeline
January - June 2001

Jan 11-Feb 4
Pilot Orientation/Training (4 Sites)

Feb 11
Release of Updated DGMS
Focus: Intake Module

Feb 14-18
Pilot Exercises and Change Requests

Feb 10-11
JAD/Program Area Meetings

Feb 24
DGMS Briefing for 0MB

Feb 25
DGMS Briefing for Deputy Secretary and Asst. Secretaries

Feb 28
DGMS Briefing for the Public Interest Groups

March I
Update all Program Templates in DGMS

March 10
Deputy Secretary's Response Due to 0MB

March 10
Release of Updated DGMS
Focus: Evaluation and Award Modules

March 13-17
Pilot Exercises and Change Requests

March 22
JAD Review

April 14
Release of Updated DGMS
Focus: Grant Administration/Drawdown Module

April 17-21
Pilot Exercises and Change Requests

April 26
JAD Review

May 12
Release of Updated DGMS Performance Management/Closeout Module, Reports and System Administration Utilities

May 15-19
Pilot Exercises and Change Requests

May 24
JAD Review

June I
DGMS to Test Center

June 30,2000
DGMS Release to Production (Tier 1)

Dec. 30,2000
DGMS Release to Production (Tier 2)

June 30,2001
DGMS Release to Production (Tier 3)